BOLUDA TRAMONTANA: NEW BOW CONSTRUCTION
Renovation of a block from the fore peak of the “Boluda Tramontana” tugboat.
Given the absence of construction plans, measurements were taken of the block to be built, to perform the exploded drawings of all components.
Once the plans were drafted and tested, the block was constructed in the workshop, while the old metal was scrapped and the ship was prepared for receiving the new component.
Once the block was built in the workshop, it was transferred by special transportation and once there, assembly, adjustment and welding work was completed.
Given the absence of construction plans, measurements were taken of the block to be built, to perform the exploded drawings of all components.
Once the plans were drafted and tested, the block was constructed in the workshop, while the old metal was scrapped and the ship was prepared for receiving the new component.
Once the block was built in the workshop, it was transferred by special transportation and once there, assembly, adjustment and welding work was completed.





Contact
If you have any questions, please get in touch with us using this simple form. We will contact you shortly. Thank you.
Location
España

C. Ciudad de Sevilla 49 Polígono Industrial Fuente del Jarro 46988 Paterna - Valencia (Spain)
Phone: +34 96 367 42 16
Email: [email protected]
Phone: +34 96 367 42 16
Email: [email protected]
Cargando ...